AUTH/2618/7/13 - AstraZeneca v Chiesi

Promotion of Fostair

  • Received
    22 July 2013
  • Case number
    AUTH/2618/7/13
  • Applicable Code year
    2012
  • Completed
    10 December 2014
  • No breach Clause(s)
    9.1
  • Breach Clause(s)
    7.2 and 7.4
  • Sanctions applied
    Undertaking received
  • Additional sanctions
    Audit of company’s procedures
    Re-audit
  • Appeal
    PMCPA panel reported company to the Appeal Board
  • Review
    February 2015

Case Summary

AstraZeneca complained about a Fostair (formoterol/beclometasone pressurised inhalation solution) leavepiece issued by Chiesi. AstraZeneca marketed Symbicort (budesonide/formoterol turbohaler). Both medicines were indicated in the regular treatment of asthma where use of a combination (inhaled corticosteroid (ICS) and long-acting ß2 adrenoceptor agonist (LABA)) was appropriate.

The detailed response from Chiesi is given below.

AstraZeneca alleged that 'for an extra fine day', immediately below 'New licence for Maintenance And Reliever Therapy' on page 1 of the leavepiece, was an unqualified and unsubstantiated claim for Fostair which suggested that patients returned to an improved pre-symptom state with Fostair; the illusion was compounded by the illustration.

The Panel noted that 'for an extra fine day' appeared within the headline 'New licence for Maintenance And Reliever Therapy for an extra fine day'. The Panel noted that 'extra fine' in the claim at issue had been written as two words. It appeared as one word 'extrafine' in the SPC when describing the formulation.

The Panel accepted that the use of 'for an extra fine day' was a play on words but considered that the heading to page 1 was not sufficiently clear about what 'extra fine' referred to, there was an implication that it referred to a clinical benefit and not just to the product's formulation as submitted by Chiesi and it was ambiguous in this regard. 'Extra' by implication rendered the claim 'for an extra fine day' comparative; use of the product for the new licence provided an extra clinical benefit over and above an appropriate comparator. This implication was misleading. Chiesi provided no data to support such an advantage. The Panel noted AstraZeneca's submission that there was no robust clinical evidence to show that Fostair's extrafine formulation translated into a clinical benefit compared with other licensed treatments.

The Panel did not consider that, within the context of the front page of the leavepiece, the heading and the image of a woman in a field with her arms outstretched implied that patients would return to a pre-symptom state with Fostair as alleged.

The Panel considered that the claim 'New licence for Maintenance And Reliever Therapy for an extra fine day' was ambiguous, misleading and could not be substantiated. Breaches of the Code were ruled. The Panel did not consider that in these circumstances Chiesi had failed to maintain high standards and no breach of the Code was ruled.

Following notification of the Panel ruling AstraZeneca wrote to the Authority, noting, inter alia, that it was surprised by the first paragraph of the Panel ruling which implied that during intercompany dialogue EXTRA FINE was put into upper case for emphasis as the leavepiece provided by Chiesi used lower case letters only within the claim at issue. This was at odds with the leavepiece upon which AstraZeneca had based its complaint, a copy of which it now provided.

Chiesi returned the signed undertaking on 4 September. On 11 September, before the Authority had contacted the company about this matter, Chiesi advised the Authority that a product manager had unilaterally altered the leavepiece after it had been electronically certified such that 'extra fine' read 'EXTRA FINE'. Chiesi was asked to explain the circumstances.

Following receipt of the additional information from both parties the original Panel reconvened to consider the matter in relation to Paragraph 8 of the Constitution and Procedure. Chiesi was so informed and asked to provide detailed comments which are summarized below.

The Panel considered the matter in relation to Paragraph 8.2 of the Constitution and Procedure which provided that the Panel might report a company to the Appeal Board. Such a report might be made notwithstanding the fact that a company had provided an undertaking requested by the Panel.

The Panel noted that it had considered the complaint in relation to the copy of the leavepiece provided by Chiesi in its response to the complaint, which bore the correct reference number and featured the claim 'extra fine' in lower case. The Panel noted that this version of the leavepiece had never been distributed. According to Chiesi, a product manager had unilaterally altered the leavepiece such that the claim in question was in upper case ('EXTRA FINE') and thus aligned with other Fostair materials. The signatories certified a printed version of a PDF file which had previously been electronically approved in Zinc. It was wrongly assumed that no changes had been made to the previously approved artwork. It appeared that it was this version that was provided to the Panel rather than the item in its final form as amended by the product manager. Chiesi stated that the employees in question had clearly acted outwith the company's standard operating procedure (SOP). It was not known why he/she had not followed the relevant SOP.

The Panel did not accept Chiesi's conclusion that this was evidence of a lone employee failing to accord with approved SOPs. Firstly, the Panel noted that other Chiesi employees had been copied in on the relevant employee's emails to the agency. Secondly in the Panel's view, it should have been abundantly clear to each signatory that the version provided for certification was not in its final form as required by the Code and the relevant SOP. In the Panel's view, this raised concerns about the competence of each of the Code signatories given each had certified that they had examined the final form of the material.

The Panel considered that the failure of both the product manager and the signatories to adhere to the SOP was a matter of concern and raised questions about the importance of compliance within the company.

The Panel expressed concern about the certification arrangements.

The Panel was extremely concerned that Chiesi's response to the complaint quoted throughout the claim at issue in upper case whereas the leaflet supplied used lower case for 'extra fine'. The Panel was concerned that Chiesi had not noted the discrepancy on a number of occasions through from approval, inter-company dialogue and its response to the complaint. That the company only became aware of the matter when it was notified of the Panel's rulings was unacceptable. It further transpired that the company's original undertaking in this case incorrectly stated that the material was last used on 17 March 2013 and that was not so. A revised undertaking with a later date of final use had been provided. The Panel noted that an undertaking was an important document and the Authority must be able to rely on its accuracy.

The Panel was extremely disappointed by the conduct of Chiesi as outlined above. Self-regulation relied, inter alia, upon the provision of complete and accurate information to the Panel. Its previous conduct in this regard was not irrelevant. The Panel considered that the circumstances warranted reporting the company to the Appeal Board under Paragraph 8.2 for it to consider in relation to Paragraphs 11.3 and 11.4 of the Constitution and Procedure.

On considering the report the Appeal Board noted that as a result of staff failing to follow the relevant company SOP, the final printed version of the leavepiece at issue featured 'EXTRA FINE' in upper case whereas the Zinc copy approved by Chiesi's signatories featured 'extra fine' in lower case. Chiesi had provided the Zinc 'lower case' copy of the leavepiece in its response to the complaint without checking that that copy matched the final printed file 'upper case' copy; this despite the fact that in inter-company dialogue and throughout the complaints procedure, both parties had consistently referred to 'EXTRA FINE' in upper case. In the Appeal Board's view, the discrepancy between the two versions of the leavepiece should have been obvious to Chiesi from the outset. Chiesi had not certified the final form of the leavepiece. The PDF certified was not the final form as some of the pages were not the correct size and, in addition,the version certified used 'extra fine' in lower case and not 'EXTRA FINE' in upper case as on the final version. Neither the product manager nor the signatories had followed the company's SOP.

The Appeal Board also noted with concern that Chiesi's original undertaking and assurance in respect of the breaches ruled in this case was incorrect with regard to the final date on which the leavepiece was used.

The Appeal Board noted Chiesi's submission that the failure to follow the correct approval process, and to recognise the difference between the approved leavepiece and the one that was distributed, and the mistakes in the undertaking arose from human error and lack of attention to detail. In that regard the Appeal Board noted Chiesi had previously been censured for providing the PMCPA with inaccurate information (Case AUTH/2435/8/11). In that case the Appeal Board decided that Chiesi should be publicly reprimanded and it should undergo an audit of its procedures in relation to the Code to be carried out by the Authority. This was carried out in March 2012 and a second audit was required (carried out in October 2012). The report for the second audit included a recommendation that 'Chiesi needed to ensure…that all information provided to the PMCPA was accurate'. The Appeal Board considered that Chiesi's repeated failure to provide accurate information to the PMCPA was completely unacceptable.

Self regulation relied upon the provision of complete and accurate information by pharmaceutical companies. The Appeal Board was extremely concerned about Chiesi's conduct, and having considered all the sanctions available under Paragraph 11.3 of the Constitution and Procedure it decided that the company should be publicly reprimanded for providing inaccurate information to the Authority.

The Appeal Board also decided to require an audit of Chiesi's procedures in relation to the Code. Given the details of the company's ongoing and planned compliance activities, the Appeal Board decided that the audit should be conducted in five months' time (March 2014). On receipt of the audit report the Appeal Board would consider whether further sanctions were necessary.

Upon receipt of the March 2014 audit report, the Appeal Board considered that Chiesi's embarrassment at the errors which had led to the requirement for it to be audited were well founded.

The Appeal Board was extremely concerned that Chiesi had been audited twice in 2012 and that the current audit report highlighted a number of serious issues with Chiesi's compliance procedures and materials; it appeared that the company still had much work to do. The Appeal Board provided a number of detailed comments including its serious concerns that Chiesi had stated that a standard operating procedure had been updated when it had not. The Appeal Board was appalled that, in this regard, it appeared that Chiesi had yet again provided false information to the PMCPA; thiswas completely unacceptable. The Appeal Board considered that its further concerns about the provision of false information should be added to the detail of that public reprimand. The Appeal Board was also concerned about the outcome of Chiesi's job bag audit (conducted by an external compliance consultant). A second job bag audit was due in April 2014 and the Appeal Board requested that the results, which needed to show a significant improvement, be provided at the next PMCPA audit.

The Appeal Board noted that the company had already been given a significant amount of time to ensure its procedures, policies and culture supported a robust compliance framework. The Appeal Board decided that Chiesi should be reaudited in October 2014 when the company must be able to demonstrate significant improvement. Upon receipt of the report for the re-audit, the Appeal Board would decide whether further sanctions were necessary.

Upon receipt of the October 2014 audit report, the Appeal Board noted that Chiesi had made progress since the audit in March 2014. The Appeal Board noted that this was not the first case in which Chiesi had been censured for failing to provide accurate information; such failings were completely unacceptable and must not happen again. The Appeal Board noted that Chiesi provided details of its plans to implement the audit report recommendations. On the basis that this work was completed, progress was continued and the company wide focus on compliance was maintained, the Appeal Board decided that, on balance, no further action was required.